MS1.1 – Power Module Mission Profile: Completed

MS3.1 – State of the Art Review of active filters: Completed

MS2.1 – State of the Art review on arcs and PD detection: Completed

MS4.1 – Power Converter PDR: Completed

MS5.1 – Launch of CDE plants: Completed

MS1.2 – FEM based lifetime model: By the end of June 2026

MS1.3 – Initial implementation of HF-PCT: By the end of September 2026

MS1.4 – Initial implementation of PCsec and PCmin: By the end of September 2026

MS4.2 – Power Converter CDR: By the end of September 2026

MS5.2 – Gate Review: By the end of September 2026

MS2.2 – Start of test: By the end of October 2026

MS3.2 – Selection of components for hybrid EMI filter: By the end of November 2026

MS3.3 – Component selection and optimization of active DM filter: By the end of November 2026

MS4.3 – Power Converter Test Plan: By the end of November 2026

2027

MS2.3 – AFD&PD data available: By the end of January 2027

MS2.4 – AFD&PD algorithms: By the end of April 2027

MS3.4 – Hybrid EMI filter assembling and test: By the end of May 2027

MS3.5 – Active DM filter assembling and test: By the end of May 2027

MS1.5 – Experimental results: By the end of July 2027

MS3.6 – Results of compliance of power converter: By the end of October 2027

MS4.4 – Test Report: By the end of October 2027